# Gantt

> Part of the NocoDB documentation (Product docs > Tables > Views > View Types). Index of all pages: https://nocodb.com/llms.txt. Any docs page is available as Markdown by adding `.md` to its URL.

URL: https://nocodb.com/docs/product/tables/views/view-types/gantt
Last updated: 2026-09-25

Learn how to work with Gantt view in NocoDB.

Plan sprints, track roadmaps, and manage dependencies. All from the same table you already use. Gantt View turns any date-based table into a live project schedule, where records become draggable bars on a timeline, dependencies become arrows between them, and key dates become milestone diamonds.

Drag to reschedule, resize to extend, and pull from a bar's handle to link tasks together. Zoom from a one-week sprint all the way out to a five-year roadmap without changing views.

This section covers everything you can do in the Gantt view.

<img alt="Gantt View Overview" src={__img0} placeholder="blur" />

<AskNocoAI>
  <Prompt>
    Create a gantt view of this table using [Start Date] and [End Date]
  </Prompt>

  <Prompt>
    Create a gantt view of [Tasks] for the [Website Redesign] project
  </Prompt>

  <Prompt>
    Add [Start Date] and [End Date] fields and create a gantt view
  </Prompt>
</AskNocoAI>

## Gantt View Actions

1. [Create a New Gantt View](/docs/product/tables/views/create-view#create-new-view)
2. [Rename an Existing Gantt View](/docs/product/tables/views/actions-on-view#rename-view)
3. [Duplicate a Gantt View](/docs/product/tables/views/actions-on-view#duplicate-view)
4. [Remove a Gantt View](/docs/product/tables/views/actions-on-view#delete-view)
5. [Share a Gantt View](/docs/product/tables/views/share-view)
6. [Lock Gantt View for Edits](/docs/product/tables/views#view-permission-types)

## Configure Gantt Schedule

Gantt View renders bars and arrows from a per-view **Date Dependencies** rule. When a Gantt view is first opened, the **Configure Gantt Schedule** dialog opens automatically so you can pick the fields that drive the chart.

<img alt="Configure Gantt Schedule dialog" src={__img1} placeholder="blur" />

The dialog accepts the following fields:

| Field            | Required | Purpose                                                                                                                                                                                                            |
| ---------------- | -------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ |
| Start Date       | Yes      | The Date field used as each record's bar start.                                                                                                                                                                    |
| End Date         | Yes      | The Date field used as each record's bar end. Records without a start render as milestones at this date.                                                                                                           |
| Duration         | Optional | Number or Duration field. When set, edits to dates write back into this field, and edits to duration shift the End Date.                                                                                           |
| Successor Link   | Optional | Self-referencing Links field that points each record to the tasks scheduled **after** it. Drives the dependency arrows on the chart. Must be Has-Many, One-to-Many, or One-to-One pointing back to the same table. |
| Include weekends | Toggle   | When off, weekends (Sat/Sun) are skipped in all date calculations. Only takes effect when Duration, Scheduling Mode, or Buffer Days is configured — until then the toggle is disabled.                             |

When a Successor Link is selected, an additional **Propagation** section appears (PostgreSQL and MySQL bases only) for configuring how date changes cascade across linked records:

* **Connection Type**: `End-to-Start` (default), `End-to-End`, `Start-to-Start`, or `Start-to-End`.
* **Scheduling Mode**: `Off` (no cascade), `Flexible`, or `Fixed`.
* **Buffer Days**: Number of days between a predecessor and its successor when cascading.

<Callout type="info">
  The Gantt rule is 

  **per-view**

   — two Gantt views on the same table can pick different Start, End, and Successor Link fields. The table-level 

  [Date Dependencies](/docs/product/tables/records/date-dependency)

   rule, if any, continues to drive cascades on Grid edits independently.
</Callout>

To reopen the dialog later, click **Configure** in the toolbar.

<img alt="Configure button in toolbar" src={__img2} placeholder="blur" />

### Empty state

If the rule has not been configured (or its Start / End Date fields have been deleted), Gantt View shows an empty state with a **Configure Date Dependencies** button that opens the same dialog.

<img alt="Empty state" src={__img3} placeholder="blur" />

## Zoom Levels

Gantt View supports eight zoom levels, from a one-week sprint view out to a five-year roadmap. Switch between them using the zoom selector in the toolbar.

<img alt="Zoom Selector" src={__img4} placeholder="blur" />

| Zoom     | Span shown                         | Best for                                    |
| -------- | ---------------------------------- | ------------------------------------------- |
| Week     | Seven days (Monday through Sunday) | Weekly planning, sprint views               |
| 2 Weeks  | Two weeks                          | Fortnightly sprints, short-cycle scheduling |
| Month    | One calendar month                 | Monthly overview                            |
| Quarter  | Three months                       | Quarter planning                            |
| 6 Months | Six months                         | Half-year roadmaps                          |
| Year     | Twelve months                      | Annual planning                             |
| 2 Years  | Two years                          | Multi-year projects                         |
| 5 Years  | Five years                         | Long-range portfolio views                  |

At coarser zooms, the date header stacks multiple tiers, for example year over quarter over month, so you can keep your bearings while seeing a wider span at once.

<img alt="Year Zoom" src={__img5} placeholder="blur" />

<Callout type="info">
  Gantt View does not offer a single-day zoom. Dependency arrows and milestones need at least a one-week horizon to read clearly.
</Callout>

## Navigation

### Time Navigation

* Use the **Previous** and **Next** buttons in the toolbar to navigate backward or forward by one step of the active zoom level.
* Click the **Today** button to jump to the current date.
* Use the **Date Picker** dropdown to navigate directly to a specific date.

<img alt="Gantt Navigation" src={__img6} placeholder="blur" />

### Scrolling

* **Horizontal scrolling** pans across time. Records load progressively as you scroll, so you can browse across months or years without having to jump to a specific date.
* **Vertical scrolling** is supported when the number of records exceeds the visible height. In grouped layout, each group scrolls within the groups list while the date header stays fixed at the top.

### Record Navigation

When a record bar extends beyond the visible area, navigation arrows appear on the bar:

* A **left arrow** appears when the record's start date is clipped (off-screen to the left).
* A **right arrow** appears when the record's end date is clipped (off-screen to the right).

Click on these arrows to navigate to the corresponding date.

<img alt="Off-screen record navigation arrows" src={__img7} placeholder="blur" />

Clicking a record in the left sidebar also pans the date axis when the bar is fully off-screen; if any part of the bar is visible, the timeline stays put so vertical scrolling does not disturb your horizontal position.

## Record List Sidebar

The left sidebar lists every record currently in view. It is **collapsible** (click the chevron at the top of the sidebar) and **resizable** (drag its right edge). Width and collapsed state are persisted across sessions.

<img alt="Sidebar collapse and resize" src={__img8} placeholder="blur" />

When collapsed, the sidebar shrinks to a slim "Show Sidebar" stub so the chart can use the full width.

<img alt="Collapsed sidebar" src={__img9} placeholder="blur" />

Click a record in the sidebar to open the [Record Inspector](#record-inspector) for it.

## Bars and Milestones

### Task bars

Records that have both a start date and an end date render as horizontal bars spanning from start to end. Hover a bar to see a tooltip with the record title, date range, and duration.

<img alt="Task bar tooltip" src={__img10} placeholder="blur" />

### Milestones

Records that have **only an end date** (start date empty) render as a diamond at the end-date column. Milestones still appear in the sidebar (with a small diamond marker on the right edge of the row so they are recognisable even when the bar is off-screen), can act as a predecessor or successor in a dependency chain, and can be dragged to a different date just like a bar.

Each milestone also drops a subtle dashed vertical guide line from the date header down to the milestone diamond, similar to the "today" line, so you can read a milestone's date against the header at a glance.

<img alt="Milestones" src={__img11} placeholder="blur" />

In the example below, the selected `Design Sign-off` milestone shows its dashed guide line running up to the date header, with the record inspector confirming it as a milestone with only an end date:

<img alt="Milestone guide line" src={__img12} placeholder="blur" />

## Edit Record Dates

**Drag to Move**
Click and hold a bar briefly, then drag it to a new date position. Both the start and end dates shift by the same number of days, preserving the record's duration. Milestones can be dragged to change their end date.

**Drag to Resize**
Hover over the left or right edge of a bar to reveal a resize handle:

* Drag the **left edge** to change the start date.
* Drag the **right edge** to change the end date.

<img alt="Drag to move and resize" src={__img13} placeholder="blur" />

<Callout type="info">
  Drag-to-move and resize operations support undo / redo.
</Callout>

## Dependencies

When a Successor Link field is configured, Gantt View draws arrows from each record to the tasks it points at (its successors).

### Create a dependency

Hover over a bar to reveal a small circular **dependency handle** at the bottom-right corner (bottom tip for milestones). Click and drag from the handle onto another bar to create the link. The cursor draws an L-shaped preview while you drag.

<img alt="Drag to create dependency" src={__img14} placeholder="blur" />

### Highlight the chain

Hovering any bar or milestone outlines its **entire connected dependency chain** in green, both upstream and downstream. When the inspector is open, the inspected record's chain stays highlighted so you can keep your context while scrolling.

<img alt="Chain highlight" src={__img15} placeholder="blur" />

### Remove a dependency

Click the dependency arrow to select it, then press <kbd>Delete</kbd>, or remove the link from the [Record Inspector](#record-inspector).

## Record Inspector

Clicking a bar, milestone, or sidebar row opens the **Record Inspector** in a right-rail panel. The inspector lets you keep panning and zooming the chart while inspecting one record.

<img alt="Record Inspector" src={__img16} placeholder="blur" />

The inspector shows:

* A **Record** or **Milestone** badge and the date range.
* The **primary field** (record title), editable inline.
* **Start Date**, **End Date**, and **Days** (computed) fields. Click a date to open a picker.
* **Predecessors** section: every record that points to this one. Click `+ Link record` to add, click the `×` next to a chip to remove.
* **Successors** section: every record this one points to. Same link / unlink controls.

Formula fields whose output is a URL render as clickable links in the inspector.

Click the **Expand** icon in the inspector header to open the full expanded record form for the same record. Press <kbd>Esc</kbd> to close any open picker first, then the inspector itself.

A second click on the **same** bar (the one already showing in the inspector) escalates straight to the full expanded form, matching the two-tier reveal pattern in other views.

## Add New Records

There are two ways to add records in Gantt View:

**Using the Add Button**
Click the floating `+` button at the bottom-left of the chart. A new record is created with the start and end dates set to the currently visible date range, and the expanded record form opens.

**Drag to Create**
Click and drag on an empty area of the Gantt grid to create a new record:

1. Click on the starting date and drag to the ending date.
2. A dotted selection rectangle shows the date range being selected.
3. Release to create the record. The expanded form opens with the start and end dates pre-filled.

<img alt="Drag to create a new record" src={__img17} placeholder="blur" />

<Callout type="info">
  Drag-to-create is available only in flat (non-grouped) layout.
</Callout>

## Customize Record Label

You can customize the fields displayed on record bars. Click the `Fields` menu in the toolbar:

* Toggle fields on or off to control which fields are shown on the bars.
* Reorder fields using drag and drop.
* Apply text formatting (Bold, Italic, Underline) to individual fields.

<img alt="Fields Menu" src={__img18} placeholder="blur" />

## Grouping Records

You can group records by one or more fields using the `Group By` option in the toolbar. When grouping is active:

* Records are organized into collapsible groups in the left sidebar.
* Each group displays its own chart segment with a record count.
* The date header stays fixed at the top while groups scroll vertically.
* Dependency arrows that span groups are rendered above the groups list so chains stay visible across group boundaries.

<img alt="Gantt Group By" src={__img19} placeholder="blur" />

Each group-by entry in the `Group By` menu has an enable/disable toggle, so you can switch a grouping off and back on without losing its configuration.

<Callout type="info">
  Sort is intentionally omitted from Gantt View — records are ordered by start date so vertical position lines up with chronology.
</Callout>

## Visual Indicators

* **Today's date**: Highlighted with a distinct background colour and blue text.
* **Weekends**: Displayed with a light grey background.
* **Record colours**: When [Row Coloring](/docs/product/tables/table-operations/record-colouring) is configured, the colour applies to the bar as a background fill, a left-edge accent stripe, or both, depending on the rule.
* **Hover**: Hovering a bar shows a tooltip with the record title, date range, and duration. Hovering also highlights the bar's entire dependency chain.
* **Inspected record**: The bar (or milestone) currently shown in the Record Inspector is outlined in the brand colour.

## Shared and Public Views

Gantt views can be shared via the standard [Share View](/docs/product/tables/views/share-view) flow. In a public / shared view:

* Bars, milestones, and dependency arrows render normally.
* The Record Inspector is **read-only**: name and date fields are not editable, and the Link record / Unlink controls are hidden.
* Bar drag, resize, and the dependency handle are disabled.

<img alt="Shared public Gantt view" src={__img20} placeholder="blur" />

## Other Toolbar Operations

1. [Apply Filters to Display Specific Records on the Gantt](/docs/product/tables/table-operations/filter)
2. [Perform Quick Searches for Specific Data Within Fields](/docs/product/tables/table-operations/search)
3. [Export Data to CSV or Excel Format](/docs/product/tables/table-operations/download#download-data)
4. [Apply Row Coloring Based on Field Values](/docs/product/tables/table-operations/record-colouring)

<Callout type="info">
  Gantt View is not supported on mobile. Open the view on a desktop or tablet to schedule records.
</Callout>

## Availability

* Gantt View is available on **NocoDB Cloud** (Business plan and above) and licensed self-hosted deployments (Business plan and above).

## Related

[Timeline View](/docs/product/tables/views/view-types/timeline)
[Calendar View](/docs/product/tables/views/view-types/calendar)
[Date Dependencies](/docs/product/tables/records/date-dependency)
[Grid View](/docs/product/tables/views/view-types/grid)

---

## Related pages

- [Grid](https://nocodb.com/docs/product/tables/views/view-types/grid.md): Learn how to work with grid view in NocoDB.
- [Gallery](https://nocodb.com/docs/product/tables/views/view-types/gallery.md): Learn how to work with gallery view in NocoDB.
- [Form](https://nocodb.com/docs/product/tables/views/view-types/form.md): Learn how to create, import, and manage forms in NocoDB.
- [Kanban](https://nocodb.com/docs/product/tables/views/view-types/kanban.md): Learn how to work with kanban view in NocoDB.
- [Calendar](https://nocodb.com/docs/product/tables/views/view-types/calendar.md): Learn how to work with Calendar view in NocoDB.
- [List](https://nocodb.com/docs/product/tables/views/view-types/list.md): Learn how to work with List view in NocoDB.
- [Map](https://nocodb.com/docs/product/tables/views/view-types/map.md): Learn how to work with Map View in NocoDB.
- [Timeline](https://nocodb.com/docs/product/tables/views/view-types/timeline.md): Learn how to work with Timeline view in NocoDB.